Cost control and profitability for interior design projects
Am I making money on this project? Compare margin, estimated costs and actual spend in one panel. Formulas, variance and budget-vs-payments reconciliation.
Cost control and profitability in interior design answer two questions in one panel: am I making money on this project? and does the budget match actual spend? Profitability is revenue minus costs; margin expresses that result as a percentage. Reconciling estimated vs actual and payments vs purchase orders prevents discovering a loss at handover.
In Veta both readings come from the same cost-control module: estimated and actual totals, variance per line, product margin and — on Pro — payment coverage on purchase orders.
Am I making money on this project?
Profitability is what remains after costs attributable to the job. Track three figures:
| Metric | Formula | What it answers |
|---|---|---|
| Revenue | Fees + sales + approved extras | What will you earn? |
| Gross profit | Revenue − direct costs | What remains before overhead? |
| Gross margin | Gross profit / revenue × 100 | How much of each euro remains? |
margin = (revenue − costs) / revenue × 100
Illustrative example: healthy margin
- Agreed revenue: €15,000
- Direct costs: €10,500
- Gross profit: €4,500
- Gross margin: 30%
Product margin
Sell a table for €1,200 with €800 cost: profit €400, margin 33.3%. Veta totals product cost and sale price without spreadsheet formulas.
Mistakes that shrink margin
- Watching sold amount without committed cost.
- Mixing client price and supplier cost without a clear rule.
- Waiting until the end to log actual spend.
- Not separating products, fees, construction and external services.
- Absorbing extras without recording impact.
Budget versus actual spend
Reconciliation means comparing the financial plan with reality while the project runs:
- Costs: estimated vs actual — am I overrunning?
- Payments: budgeted vs paid — am I financing the client's job?
Variance per line
variance = (actual − estimated) / estimated × 100
| Variance | Reading |
|---|---|
| Above +5% | Overrun to review |
| Between −5% and +5% | On plan |
| Below −5% | Saving |
| No actual yet | Pending |
Illustrative example: carpentry estimated €3,000, invoice €3,600 → +20%. You know where to look before close.
Purchase orders and payments (Pro plan)
Each payment can link to a purchase order. Veta marks coverage covered, partial or pending, so you know whether the client funded the buy before you confirm with the supplier.
Unbudgeted costs
Add a new line with the actual amount. It increases total actual even without an estimate. If you pass it to the client, record the payment as an additional cost.
Internal costs vs client view
The client budget shows sale prices, not your margin. Internal-cost lines stay out of the public view and PDF on compatible plans.
Which plan you need
Estimated vs actual: all plans. Purchase orders, payments and coverage: Pro plan. Full comparison on pricing.
FAQ
How do I know if a project is profitable before close?
Update revenue and costs weekly and calculate margin with current figures, not only the original budget.
What is gross margin?
Revenue minus direct costs as a percentage of revenue.
What does reconciling budget and payments mean?
Crossing estimated vs actual per line and payments vs purchase orders while the job is still open.
Does Veta read invoices or the bank?
No. You enter amounts; Veta calculates totals, variance and coverage.
Can I hide internal costs?
Yes — flag lines as internal so they stay out of client views and documents.
Which variance should I review first?
Those over 5%, high amounts, or pending purchases you cannot pass on to the client.